Europe Cargo was approached for the reception in Antwerp ex geared coaster up to barged to Fluor Terminal Frankfurt, Germany. The vessel, MV Jumbo Vision loaded in Punta Cugno, Italy and sailed from Punta Cugno port. The project consisted of 37 pieces of preassembled steel rack (858.303 mt / 14,095.695 m3), two cases of lifting equipment (2,276 mt / 6 m3) and eight pieces of lifting equipment (adjustable spreader bars / extenders: 7478 mt / 18 m3).
Europe Cargo’s supervisor reported that the cargo was loaded under deck as well as on deck. On Europe Cargo’s instructions, the crew unlashed the chains and unwelded stoppers and D-rings upon arrival at the Antwerp port.
The cargo was unloaded at the Europe Cargo terminal with specialized and necessary stevedore lifting equipment (extenders – easily adjustable) and by two Gottwald motorized mobile cranes with capacities of 100 mt (not by ship’s gear due to outreach and storage onto the shore and two cranes instead of one due to length of the cargo).
Due to the large storage area required, MV Jumbo Vision had to shift 40 m. Europe Cargo jointly surveyed unloading operations with the receiver’s appointed surveyors. Europe Cargo also arranged customs clearance in Antwerp. After unloading, necessary repairs and cleaning of the frames was arranged and took several days. When this was completed Europe Cargo ordered and arranged loading of four barges (110 m x 45 m) for the inland transport via Rhine river to the final Frankfurt site.
Europe Cargo’s profressional expertise in the project was highly appreciated by the receivers’ engineers!
The Global Project Logistics Network (GPLN) is the premier non-exclusive professional projects logistics network of independent companies specializing in international projects movements by air, sea and land as well as specialized lifts and the special handling of oversized, out-of-gauge and heavy lift cargo.
![]() |